The Contractor Says 80% Done. You Think 50%. Here's How to Settle It.

🏗️
AEDO Engineering
AEDO Construction OPC, PRC-licensed civil engineers. Stage weights are from AEDO's published 2026 house cost breakdown. Article 1724 is quoted from the Civil Code.

Short answer: an argument about how finished a house looks can go in circles. An independent verification ends it, because it measures the work in place against the contract scope and turns it into a percentage of contract value. Get it done before you release the next payment and before either side walks away, and make sure the report says plainly what it could and couldn't see.

It can surface at a billing. The statement of work accomplished says one number, your eyes say another, and the contractor is waiting to be paid. You don't want to be cheated. You also don't want to be the owner who stalled a project over a hunch. That's exactly the gap an engineer's report is for.

Concrete being poured on a construction site
Once it's covered by finishes, concrete and the steel inside it can only be verified from earlier records. Illustrative image.
Free Gap Check · By AEDO Construction

Claimed vs Actual Progress Check

Mark each stage of a house as you see it. The check weights them by their share of contract value, compares that with the contractor's claim and with what you've paid, and says what kind of verification the gap needs.

What this is and is not. A way to see the size of a disagreement before paying anyone to settle it. The weights describe a typical house, not your contract, and "half done" is your own judgement. A sealed verification works from your actual scope and quantities.
Billing on hold right now? Send the contract, the statement of work accomplished and dated photos, and we'll tell you whether a desk review is enough. Request a progress verification →

Why the House Looks Further Along Than It Is

Our progress billing guide weights a Philippine house by cost. With the roof on and the walls up, the work in place is about 55 percent of the money, even though it can feel 80 percent finished. Tiles and finishes alone are nearly 15 percent, and the rough-ins buried in walls and slabs are almost invisible. A claim that tracks how the house looks will run ahead of what's been built.

Figure: Looks Finished vs Is Paid For Roof on, walls up: how it feels vs what it's worth How finished it looks ~80% Cost-weighted progress 55% Still to come: rough-ins 8.4% · doors, windows, ceiling 11.2% · tiles, finishes 14.6% · painting 4.5% · fixtures 6.2% Weights from AEDO's published 2026 house cost breakdown
The expensive finishing trades come last. That's why a billing that follows appearance runs ahead of value in the second half of a build.

Desk Review or Site Verification?

A desk review works from the contract, the statement of work accomplished and dated photos. It's quicker and cheaper, and for visible work it's reliable. What it can't do is verify concealed work, like reinforcement inside concrete or conduits behind plaster, or judge workmanship quality. A site verification adds measurement and inspection, and can open up where hidden work is disputed. Whichever you choose, the limitation belongs on the face of the report, because a report going into a dispute that overstates what it saw doesn't help either side.

What to Send

When the Contractor Asks for More Money

On a stipulated-price contract, Article 1724 of the Civil Code bars the contractor from demanding a higher price on account of increased labour or material costs, unless the change in plans was authorised in writing by the owner and the additional price was agreed in writing by both. Verbal "extras" are the first thing to separate from the accomplishment figure. If the dispute doesn't settle, our contractor dispute guide covers barangay conciliation, small claims, CIAC and PCAB.

Where These Figures Come From

Stage weights are from AEDO's published 2026 house construction cost breakdown, as used in our progress billing guide. The price rule is Civil Code Article 1724. The desk review limitations reflect what a photo-based review can and cannot establish, and they should appear in any report built that way.

Frequently Asked Questions

What does an independent progress verification check?

It compares the work actually in place against the contract scope and the contractor's statement of work accomplished, item by item, and gives the accomplishment as a percentage of contract value rather than an impression of how finished the house looks. The report states what was verified, how, and what could not be.

Can an engineer verify progress from photos alone?

Partly. A desk review from dated photos of every room and elevation can confirm visible work against the scope. It cannot verify concealed work, such as reinforcement inside concrete or conduits behind plaster, and it cannot judge workmanship quality. A credible report says that on its face. Where hidden work is disputed, earlier-stage photos or a site visit are needed.

What documents should I prepare?

The signed contract and its scope, the bill of quantities or cost breakdown if there is one, every statement of work accomplished and billing received, proof of payments made, any written change orders, and dated photos: every room, every elevation, one wide and one close shot per area, plus any earlier photos showing work now hidden behind finishes.

Can the contractor charge more for changes?

On a stipulated-price contract, Article 1724 of the Civil Code bars the contractor from demanding an increase in the price on account of higher labour or material costs, unless the change in plans and specifications was authorised in writing by the owner and the additional price was agreed in writing by both parties.

What happens after the verification?

Once both sides have the same numbers in front of them, there is a basis to settle. If that does not happen, the report becomes the evidence in whichever forum hears the claim. Our guide to contractor disputes sets out the four routes, including barangay conciliation and small claims.

Sources

Statute and figures used in this guide. Links open in a new tab.

Stage weights describe a typical house and are AEDO's own published figures. A verification of a real project works from that project's scope and quantities.

Get the Accomplishment Verified Before the Next Payment

One documented number both sides can work from, with its limits stated plainly.

  • Accomplishment measured against your contract scope
  • Desk review from documents and photos, or site verification where needed
  • Written report stating what was and wasn't verified