Download the Specimen PDF →
Free Resource · Specimen Document · Philippines

A Structural Assessment Report, Start to Finish

What this is

Most people commissioning a structural assessment have never seen one. So here is a complete report, written the way we write ours, with every section filled in rather than described.

It is a specimen. The building, its location and all of its findings are illustrative. No client information appears in it, and the signature, PRC licence number and dry seal are deliberately left out — a sealed document is a professional instrument, not a sample.

Download the specimen PDF 10 pages · PDF · no email required
Reading it as a checklist? Turn on the notes to see why each section exists and what a weak report leaves out.
AEDO CONSTRUCTION OPCSTRUCTURAL ASSESSMENT REPORT · AEDO-SA-SPECIMEN-01
Specimen document. The building, its address and every finding below are illustrative and do not describe any real property. The PDF version adds the cover page, document control, contents, the crack location sketch and the photographic log.

Report details

ItemDetail
Report referenceAEDO-SA-SPECIMEN-01
Subject buildingTwo-storey single-family residence, approx. 118 m² total floor area
LocationSpecimen address, Dumaguete City, Negros Oriental (withheld)
ClientProperty owner (withheld in specimen)
PurposeEvaluate reported diagonal cracking above a ground-floor window and report on the overall structural condition
Assessment typeVisual condition survey with engineering evaluation. No destructive or laboratory testing.
Prepared / reviewed byCivil engineer / principal engineer, AEDO Construction OPC (names and PRC numbers omitted from specimen)
StatusSpecimen — not for construction, permit or transaction use

Executive summary

The building is in serviceable structural condition. Of five conditions recorded, one requires repair within one month (corroding reinforcement at the entrance canopy beam, F-4), one requires monitoring over three months (diagonal cracking in an infill wall panel above window W-2, F-1), and three require no structural action. Nothing observed requires the building to be vacated, and no area needs to be taken out of use. The second floor slab carries a normal residential load satisfactorily but should be re-assessed before any additional load is added. No structural drawings were available; the evaluation rests on measured member sizes and stated assumptions.

1. Introduction and scope

AEDO Construction OPC was engaged by the property owner to inspect and report on the structural condition of the building following a diagonal crack above a ground-floor window, which the owner reported as widening over roughly six months.

In scopeNot in scope
Visual survey of the accessible frame, slabs, roof structure and visible foundationsRemoval of finishes, opening of members, or excavation to expose foundations
Measurement of recorded defects and accessible member sizesLaboratory or in-situ material testing
Engineering evaluation against NSCP 2015Architectural, electrical, plumbing, fire protection or sanitary systems
Written findings, severity classification and prioritised recommendationsDesign of any repair or retrofit (a separate engagement)
A monitoring plan where a condition needs observing over timeCertification for any regulatory, insurance or transaction purpose

2. Basis of assessment and references

ReferenceApplied to
NSCP 2015, Sec. 204Dead loads: self-weight of frame, slab, walls, roof and finishes
NSCP 2015, Sec. 205Residential live loads, including the second floor slab check
NSCP 2015, Sec. 208Seismic demand, Zone 4 site, for the frame's lateral system
NSCP 2015, Sec. 207Wind demand on the roof structure and exposed canopy
PD 1096, Secs. 214–215Dangerous-building criteria — screened against, not triggered
RA 544, Sec. 14Seal and signature requirement for the issuing civil engineer

3. Description of the building

ElementAs observed
Structural systemReinforced concrete moment frame, three bays on the north elevation (grids A to C)
Columns300 × 300 mm typical, measured at accessible faces on both levels
Beams250 × 400 mm typical at the second floor; canopy beam 200 × 300 mm
Second floor slabRC suspended slab, 3.6 m clear span in the living area, approx. 125 mm thick at the edge
Walls150 mm CHB infill, plastered both faces; non-load-bearing
RoofPre-painted metal roofing on steel purlins over a timber-framed ceiling
FoundationNot exposed. Isolated pad footings assumed, consistent with the frame and construction period

4. Methodology and instruments

ActivityMethod / instrument
Crack widthsGraduated crack comparator card, read at the widest point
Member dimensions5 m steel tape at accessible faces; plaster thickness not deducted
Column verticalitySpirit level and plumb line over 2.4 m; method tolerance approx. 3 mm
Slab deflectionString line across the span, offset measured at mid-span
Photographic recordEach frame located and dated (Appendix B of the PDF)
Concrete strengthNot tested — no cores, no rebound hammer survey
ReinforcementNot scanned; bar sizes noted only where already exposed

5. Observations

RefLocation / memberObservationMeasured
O-1Ground floor, north elevation, infill panel above window W-2, grid A-BDiagonal crack from the upper window corner toward the beam soffit, visible on both faces, partly following mortar joints and passing through blocks elsewhere2.6 mm max; 1.4 m long
O-2Ground floor, column C-3, north faceFine vertical hairline cracking over approx. 600 mm above floor. No spalling, staining, exposed bar or displacementBelow 0.3 mm
O-3Second floor slab, living area, grid B-2Slight downward deflection under normal furniture loading; ceiling line visibly curved. No soffit cracking11 mm over 3.6 m (span/327)
O-4Entrance canopy beam, exterior, grid CRust staining across the soffit; one 220 mm length of exposed, actively corroding reinforcement where cover has spalledCover loss approx. 220 × 60 mm; 1 bar
O-5Ground floor, rear service areaFloor tiles sound hollow over approx. 1.2 m². No cracking in slab below or wall aboveApprox. 1.2 m²; finish only

6. Structural evaluation

Assumptions. With no drawings available, the evaluation assumes reinforcement consistent with the bars visible at the canopy beam, concrete strength consistent with ordinary residential practice of the period, and isolated footings on undisturbed soil. Each is stated so a later engineer can test it rather than inherit it.

6.1 Gravity and live load. The 3.6 m slab's 11 mm mid-span deflection (span/327) is consistent with long-term deflection under sustained load rather than distress: no soffit cracking, and a smooth rather than locally kinked profile. The margin suits the present use and is not adequate to absorb arbitrary additional load.

6.2 Lateral system. The RC moment frame resists lateral load; CHB walls are infill and were not counted. Under NSCP 2015 Section 208 the site is Seismic Zone 4. Columns are plumb within method tolerance, no beam-column joint is cracked, and no displacement was measured across any crack.

6.3 Infill wall cracking. O-1 starts at a window corner — the stress concentration point where in-plane, thermal and shrinkage movement all collect. Its width and progression place it beyond shrinkage, but because the panel is infill, it is a serviceability and durability matter, not a loss of frame capacity.

7. Findings and severity classification

RefFindingSeverityAction
F-1Diagonal cracking in a non-load-bearing infill panel, consistent with movement rather than shrinkage. No effect on frame capacityS2Monitor
F-2Hairline surface cracking at column C-3, consistent with shrinkage. No section loss or overload patternS1None
F-3Slab deflection within the expected range for span, age and loading. No soffit crackingS1Re-assess before adding load
F-4Active corrosion with section loss at the canopy beam. Progressive if left open to weatherS3Repair within 1 month
F-5Debonded floor tiles. Finish defect, no structural componentS0Cosmetic only

8. Recommendations and indicative repair scope

PriorityActionRefers to
ImmediateNone. No condition requires the building to be vacated or any area taken out of use.—
Within 1 monthRepair the canopy beam: break back to sound concrete, clean the bar to bright metal and prime, reinstate cover with polymer-modified repair mortar, restore the drainage fall.F-4
Within 3 monthsRun the monitoring plan below on O-1. Do not fill or plaster the crack before monitoring ends — that destroys the evidence.F-1
Before any changeRe-assess the second floor slab before adding partitions, heavy storage or a water tank at that level.F-3
At next renovationRe-lay the debonded floor tiles. Cosmetic priority.F-5
Indicative cost of recommended workBand
Canopy beam concrete repair, as scoped above₱12,000 – ₱25,000
Crack monitoring points, installation and three readings₱4,000 – ₱8,000
Follow-up inspection, if monitoring is triggered₱5,000 flat
Slab re-assessment before added load, if that change is made₱5,000 flat

Indicative AEDO practice bands for Philippine work in 2026, for budgeting only — not a quotation. Testing (reinforcement scanning, and core testing under NSCP 2015 Section 426.12) is triggered only if monitoring shows growth, more corrosion appears once the beam is opened, or load is added.

9. Monitoring plan

ParameterRequirement
WhatWidth of the O-1 crack at two fixed points: window corner and mid-length
HowTwo tell-tale gauges across the crack, or paired reference pins read with a comparator card
FrequencyMonthly for three months, each reading dated and photographed
TriggerCumulative growth over 0.5 mm in three months, or any sudden increase
If triggeredFollow-up inspection, including reinforcement scanning at the adjacent columns
If notMovement is complete. Repair the crack cosmetically and close the record

10. Limitations of this report

This assessment is a professional opinion on the condition observed on the date of inspection, within the stated scope and methods. It is visual: no finishes were removed, no member was opened, and no foundation was exposed; concealed conditions are not covered. No drawings were available, so no comparison against an original design was possible. No material testing was performed. It does not certify the building as safe or constitute a certificate for any regulatory, insurance or transaction purpose, and it does not transfer liability for design or construction defects, which remains with the parties identified in Article 1723 of the Civil Code. It is valid for the condition as found and must be read in full.

11. Statement and signature

"I inspected the building described in this report on the date stated, and the observations, findings and recommendations set out here are my professional opinion, subject to the limitations in Section 10."

In a live report this is signed by the inspecting civil engineer and countersigned by the reviewing engineer, each over their printed name and PRC licence number, with the dry seal. Section 14 of Republic Act 544 requires a registered civil engineer to obtain that seal. All of this is deliberately omitted from the specimen.

Appendix C — Severity classification criteria

SeverityMeaningTypical action
S0Finish or cosmetic defect, no structural componentRepair at convenience
S1Element affected; capacity and serviceability unimpaired; stableNo action; record
S2Movement or deterioration whose progression is not yet establishedMonitor to a stated trigger
S3Active deterioration or measurable section loss; capacity not yet compromisedRepair to a defined scope and date
S4Capacity demonstrably reduced, or load path compromisedRestrict use; design a retrofit
S5Risk of collapse or harm is immediateVacate; notify the building official

AEDO's own classification, used to keep a finding's language consistent between engineers and reports. No Philippine code prescribes one. Appendices A (crack location sketch) and B (photographic log) are in the PDF.

How to use this

If you are commissioning an assessment, send this to the engineer and ask whether their report will carry these ten sections. It is a fair question and a competent engineer will say yes.

If you already have a report, read it against this one. The guide to what a structural assessment report should contain explains each section and includes a free checker that scores the document in your hands.

If you are an engineer, take the structure. The engineering cannot be borrowed — observations, measurements, findings and recommendations have to come from your own inspection of a real building, under your own seal.

Sources

Every figure, observation and finding in the specimen is illustrative. It is not an assessment of any real building and must not be presented as one.

Want the Real Thing for Your Building?

A licensed engineer inspects the structure and issues the report above with your building's actual findings in it.

  • ₱5,000 flat — site visit, NSCP 2015 evaluation, written report within 5 business days
  • A specific verdict with a timeframe: no action, monitor, restrict use, repair or retrofit
  • Testing scoped separately, only where a finding requires it
  • Site visits in Negros Oriental, Cebu, Luzon and NCR; design and assessment nationwide