Tile & Painting Cost Per Square Metre Philippines 2026

🎨
AEDO Engineering
AEDO Construction OPC — PRC-licensed civil engineers. Labour rates below match our 2026 labor rate guide; coverage figures are the manufacturers' own published values and material prices are current Philippine retail as of September 2026.

Short answer: tiling runs ₱800–₱1,400 per m² supplied and installed for ordinary ceramic, and painting runs ₱180–₱330 per m² to repaint or ₱270–₱440 per m² for the full system on new plaster. But the rate is the easy half. The half that wrecks budgets is how many square metres you actually have — because a 4 × 5 m bedroom has 20 m² of floor and nearly 50 m² of wall.

Finishing Works Is Where Budgets Quietly Break

Structure is estimated carefully because it is obviously expensive. Finishing gets a round number and a shrug — and then it comes in at 15–20% of the whole build. Our house construction cost guide puts tiles and finishes at roughly 13% and painting at another 4% of total cost. Two trades, a fifth of the money, usually the least-scoped part of the quote.

Your Walls Are Not Your Floor

This is the single biggest costing error in finishing works, and it is pure geometry. Floor area is length × width. Wall area is the perimeter × height — you walk around the room, not across it. The smaller the room, the worse the ratio gets.

RoomFloor areaWall area @ 2.7 mWall ÷ floorWhat it means
Toilet & bath, 2.0 × 2.0 m4.0 m²21.6 m²5.4×Full-height tiling here dwarfs the floor
Bedroom, 3.0 × 3.5 m10.5 m²35.1 m²3.3×Paint dominates
Bedroom, 4.0 × 5.0 m20.0 m²48.6 m²2.4×Still nearly 2.5 times
Living area, 5.0 × 7.0 m35.0 m²64.8 m²1.9×Big rooms are proportionally kinder
Whole 100 m² bungalow100 m²~260–300 m²~2.8×Includes internal partitions, both sides

Note the last row. Internal partitions get painted on both faces, which is why a 100 m² house has closer to 300 m² of paintable wall than the 100 m² its owner has in mind. Deduct doors and windows and you might get back 10–15%. You do not get back the factor of three.

Free Tool · By AEDO Construction

Tiling & Painting Cost Calculator

Give it one room's dimensions. It works out the real tiled and painted areas, costs both trades against 2026 rates, and then tells you how many tiles, bags of adhesive and cans of paint to actually buy — wastage included.

A door is ~1.7 m², a typical window ~1.5 m²
Cost bands are AEDO 2026 planning ranges for supply and install, consistent with our other 2026 cost guides — market estimates for judgement, not quotations. They move with location, delivery distance, room complexity, surface condition and access. Labour rates match our 2026 labor rate guide. Paint and putty coverage figures are Boysen's own published theoretical coverage; real coverage on rough or porous plaster is lower. Material quantities include the wastage percentage you selected and are rounded up to whole units, because hardware does not sell two-thirds of a bag.

Tiles Are Sold Per Piece. Budgets Are Counted Per Square Metre.

This is the second trap, and it catches people in the showroom. A 60 × 60 tile at ₱200 a piece looks obviously cheaper than a 60 × 120 at ₱350 — until you convert both to a price per square metre and find the small one is ₱556/m² and the big one ₱486/m². The conversion is one division, and almost nobody does it standing at the display rack.

Tile sizeArea per piecePieces per m²At ₱150/pcAt ₱250/pc
30 × 30 cm0.09 m²11.11₱1,667/m²₱2,778/m²
40 × 40 cm0.16 m²6.25₱938/m²₱1,563/m²
60 × 60 cm0.36 m²2.78₱417/m²₱694/m²
80 × 80 cm0.64 m²1.56₱234/m²₱391/m²
60 × 120 cm0.72 m²1.39₱208/m²₱347/m²

Large tiles look expensive per piece and are often cheaper per square metre. They also cut labour, since there are fewer joints to align — but only if the substrate is flat. On a wavy floor a large tile lippings and rocks, and the setter will either refuse it or spend the saved time levelling. That trade-off is real and worth asking about before you fall in love with 60 × 120.

2026 Cost Bands — Supplied and Installed

Item₱ per m²Notes
Ceramic floor tile, material350–600The default residential choice
Porcelain / homogeneous, material650–1,100Harder, lower absorption, better for wet areas
Large format 60×120 / 80×80, material1,100–2,200Needs a flat substrate and a patient setter
Granite / marble slab, material2,200–4,500Cut and polished on site; another trade entirely
Tile adhesive50–100See the bag maths below
Grout, spacers, trims, sealant40–90Routinely left out of a verbal quote
Tile setting labour350–600Pakyaw. Add ~30% for large format or stone
Paint materials — repaint57–84Two topcoats plus sundries only
Paint materials — new interior plaster146–186Primer, full putty, sanding, two topcoats
Paint materials — exterior system165–230Different filler; see below
Painting labour120–250Surface prep is most of the hours, not the rolling

Labour figures match our 2026 construction labor rates guide, where tile setters run ₱750–₱1,000/day in the provinces and ₱900–₱1,500 in Metro Manila, and painters ₱600–₱850 and ₱700–₱1,100 respectively. Pakyaw and daywork should land in roughly the same place; if they do not, one of the two is wrong about the quantity.

Where the Material Numbers Come From

Cost bands are only trustworthy if you can rebuild them. Here is the arithmetic behind the two biggest material lines, using current Philippine retail prices and the manufacturers' own published coverage.

  1. Tile adhesive. A 25 kg bag runs about ₱321 for standard grade and ₱529 for heavy-duty at Wilcon as of September 2026. Coverage is roughly 6–7 m² per bag with a 6 mm notched trowel and 5–6 m² with a 10 mm trowel, which is what large tiles need. Divide it out and you get roughly ₱46–₱106 per m² depending on grade and trowel size — hence the ₱50–₱100 band, with large format sitting at the top because it eats a deeper bed.
  2. Primer and topcoat. Boysen publishes Permacoat Flat Latex B-701 at 25–30 m² per 4 L as primer and 30–35 m² per 4 L as topcoat. A 4 L can is about ₱687, with gloss and semi-gloss at ₱792.50. One primer coat plus two topcoats therefore costs roughly ₱67 per m² in paint alone.
  3. Masonry putty. The quiet budget-killer. Boysen puts Masonry Putty B-7311 at 10–12 m² per 4 L for full puttying — about a third of the coverage of paint — against 25 m² if you are only spot-filling. On new plaster you are full puttying, so this single line can cost more than both topcoats combined.
  4. Sundries. Sandpaper, brushes, rollers, trays, masking tape, drop cloths, thinner. ₱15–₱35 per m² and never in anyone's estimate, which is why the last hardware run always feels like a surprise.
⚠️

Masonry Putty Is Interior Only — and This Is Why Exteriors Peel

Boysen specifies Masonry Putty B-7311 for interior use only. Its published exterior schedule is different: Permacoat Flat Latex as primer, then Acrytex Cast B-1711 as the filler, then two topcoats.

Using the cheaper interior putty outside is one of the most common shortcuts in Philippine repainting, and it is why so many exterior repaints blister and peel in sheets after one or two seasons of sun and rain. The putty layer holds moisture, and everything above it comes off with it. When an exterior repaint fails early, the filler underneath is the first thing to check — along with whether anyone washed and dried the wall before painting it.

Wastage Is Not Padding

Every perimeter tile gets cut, and the offcut usually cannot be used anywhere else. Standard allowances:

That last point costs more people more money than the wastage percentage itself. Tiles are fired in batches, and two boxes of the same product code bought three weeks apart can be visibly different under daylight. Order the full quantity, wastage included, at once.

What a Finishing Quote Should Actually List

A Note on These Figures

Cost bands are AEDO 2026 planning ranges for supply and install, consistent with our house construction cost and renovation cost guides. Labour rates match our 2026 labor rates guide. Material prices quoted are Philippine retail as of September 2026 and move with brand, grade and retailer. Paint and putty coverage figures are the manufacturer's published theoretical coverage on a properly prepared surface — rough, porous or previously unpainted plaster will consume more, sometimes considerably more. These are estimates for judgement, not quotations.

Frequently Asked Questions

How much does tile installation cost per square metre in the Philippines in 2026?

Supplied and installed, budget roughly 800 to 1,400 pesos per square metre for ordinary ceramic floor tile in 2026, 1,100 to 1,900 pesos for porcelain or homogeneous tile, and 1,700 to 3,200 pesos for large format tile such as 60 by 120. Those totals are made of four parts: the tile itself, adhesive, grout and trims, and labour. Labour alone is commonly quoted pakyaw at 350 to 600 pesos per square metre, with provincial ground floor work near the low end and Metro Manila or high finish work near the high end. A quote that names only a per square metre rate without saying which of those four parts it covers is not comparable to any other quote.

How much does painting cost per square metre in the Philippines?

For 2026, budget about 180 to 330 pesos per square metre to repaint a sound existing surface, 270 to 440 pesos per square metre for the full system on new plaster, which means primer, full masonry putty, sanding and two topcoats, and 290 to 480 pesos per square metre for the exterior system. Premium, textured or elastomeric finishes run well above that. Painting labour on its own is typically 120 to 250 pesos per square metre. The reason repainting is so much cheaper is that the putty and sanding stage, not the paint, is where most of the labour hours and a large share of the material cost sit.

Why is my wall area so much bigger than my floor area?

Because walls are measured around the room and up, not across it. A 4 by 5 metre bedroom has 20 square metres of floor but its four walls at 2.7 metres high come to about 48.6 square metres before deducting the door and window, roughly two and a half times the floor. Small rooms are worse in proportion: a 2 by 2 metre toilet has 4 square metres of floor and about 21.6 square metres of wall, more than five times. This is why painting and wall tiling quotes look enormous next to a floor area figure, and why budgets built on floor area alone always fall short on finishing works.

How many tiles do I need per square metre?

Divide one square metre by the area of one tile. A 60 by 60 centimetre tile covers 0.36 square metres, so you need 2.78 pieces per square metre. A 40 by 40 needs 6.25 pieces, a 30 by 30 needs 11.11 pieces, and a 60 by 120 needs 1.39 pieces. This conversion matters because tiles are sold per piece while labour and budgets are counted per square metre. A tile at 200 pesos a piece sounds cheap until you convert it: at 60 by 60 that is about 556 pesos per square metre. Always add wastage on top, about 10 percent for a straight layout, 15 percent for diagonal, and up to 20 percent for intricate or mosaic patterns.

How much area does a four litre can of paint cover?

Using Boysen's own published figures for Permacoat Flat Latex B-701, a four litre can covers about 25 to 30 square metres as a primer and 30 to 35 square metres as a topcoat. Masonry putty B-7311 covers about 10 to 12 square metres per four litres for full puttying, or about 25 square metres for spot puttying only. Those numbers are theoretical coverage on a properly prepared surface, so rough, porous or previously unpainted plaster will use more. A full three coat system on new interior plaster therefore uses roughly one can of primer and one can of topcoat per 13 to 15 square metres, plus considerably more putty than most people budget for.

Can I use masonry putty on exterior walls?

No. Boysen specifies Masonry Putty B-7311 for interior use only, and its published exterior schedule uses a different filler, Acrytex Cast B-1711, over the same flat latex primer before the topcoats. Using interior putty outside is a common and expensive shortcut in Philippine repainting work, because the putty layer absorbs moisture and the finish blisters and peels off in sheets within a season or two of sun and rain. When a repaint fails early on an exterior wall, the wrong filler underneath is one of the first things worth checking, along with painting over a damp or unwashed surface.

Get the Quantities Before You Get the Quotes

Most finishing disputes are quantity disputes wearing a price costume. An itemised take-off means every contractor prices the same square metres, and you can tell which quote is actually cheaper.

  • Itemised BOQ with finishing works measured room by room — from ₱3,000
  • Structural design and sealed plans, priced by floor area
  • Structural assessment at ₱5,000 flat if you are renovating an older house
  • Design and build for Negros Oriental; design and remote oversight nationwide