Building Permit Fee Calculator — What PD 1096 Actually Charges

🧾
AEDO Engineering
AEDO Construction OPC — PRC-licensed civil engineers. Every rate on this page was read from the text of the 2004 Revised IRR of PD 1096 and the 2019 Revised IRR of RA 9514, not from a summary.

Short answer: the government fee is smaller than people fear, and it is assembled from more pieces than they expect. A 200 sqm house carries a building fee of about ₱1,440 — that is the headline number. What makes the real total is everything around it: four or five ancillary permits, line and grade, the occupancy certificate, and the FSEC at 15% of everything the building official collects.

The Mistake Almost Every Online Permit Calculator Makes

Residential building fees are NOT cumulative. The whole floor area is charged at the single bracket rate. The IRR's own worked example: 75 sqm falls in the ₱4.80 bracket, and the fee is 75 × 4.80 = ₱360.00 — not a stack of sub-brackets. Commercial fees are cumulative. Mixing the two up is why so many published figures are wrong.

Free Tool · By AEDO Construction

Building Permit Fee Calculator

Assembles the building fee under the correct method for your occupancy group, adds the electrical, mechanical and line-and-grade ancillary fees, the occupancy certificate and the BFP clearance, and shows the working line by line so you can check it against your assessment.

All storeys combined
From the electrical load schedule — a typical house is 10–25 kVA
0 if no aircon is in the permit application
For the line and grade fee — all sides fronting or abutting
Assessed on cost of construction, not floor area
Required before the building permit is released
Section 212 surcharges, applied to the building fee
Rates are quoted from the New Schedule of Fees and Other Charges in the 2004 Revised IRR of PD 1096, and the FSEC from Sec. 12.0.0.4 of the 2019 Revised IRR of RA 9514. This covers the building fee, the electrical and mechanical ancillary fees, line and grade, the occupancy certificate and the BFP clearance. It does not include plumbing, electronics or accessory fees, zoning and locational clearance, barangay clearance, the LGU's own local charges, or professional fees for the plans — all of which are real and vary by LGU. The building official makes the final assessment; treat this as a budgeting figure.

The Building Fee Schedule, Straight From the IRR

Division A-1 — single-family dwellings (flat rate)

Floor areaFee per sq m
Original complete construction up to 20.00 sq m₱2.00
Additional / renovation / alteration up to 20.00 sq m, regardless of the original floor area₱2.40
Above 20.00 to 50.00 sq m₱3.40
Above 50.00 to 100.00 sq m₱4.80
Above 100.00 to 150.00 sq m₱6.00
Above 150.00 sq m₱7.20

The IRR prints its own worked example immediately below this table, and it settles the cumulative question permanently: "Floor area = 75.00 sq. meters. Therefore area bracket is 3.a.iv. Fee = P 4.80/sq. meter. Building Fee = 75.00 x 4.80 = P 360.00." The entire 75 sqm is charged at ₱4.80 — the first 20 sqm is not carved out at ₱2.00.

Division A-2 — duplex and multi-family

Floor areaFee per sq m
Original complete construction up to 20.00 sq m₱3.00
Additional / renovation / alteration up to 20.00 sq m₱3.40
Above 20.00 to 50.00 sq m₱5.20
Above 50.00 to 100.00 sq m₱8.00
Above 150.00 sq m₱8.40

Read that last table carefully. It jumps from "above 50 to 100" straight to "above 150" — the published schedule has no row for 100–150 sqm in Division A-2. That is a genuine gap in the text, not a transcription error on our part. In practice building officials apply the adjacent bracket; the calculator above uses the ₱8.00 rate up to 100 and ₱8.40 beyond, which is the conservative reading.

Commercial, industrial and institutional (cumulative)

Divisions B-1 / C-1 / E-1,2,3 / F-1 / G-1–5 / H-1–4 / I-1 and J-1,2,3 are assessed cumulatively: ₱23.00/sqm for the first 5,000, then ₱22.00, ₱20.50, ₱19.50, ₱18.00, ₱17.00, ₱16.00, ₱15.00, ₱14.00 and ₱12.00 above 30,000 sqm. Divisions C-2 / D-1,2,3 follow the same method at roughly half the rates, starting at ₱12.00 and ending at ₱5.00. Division J-2 structures — garages, carports, fences over 1.80 m, tanks, pools, towers — are assessed at 50% of the rate of the principal building they belong to.

🔎

A Typo in the Published Schedule Worth Knowing About

The commercial table's seventh row reads "Above 1,000 to 1,500" where the sequence plainly requires "Above 10,000 to 15,000". The IRR's own sample computation for a 32,000 sqm building confirms the intended reading — it applies ₱16.00 to the 5,000 sqm running from 10,000 to 15,000. If you are checking an assessment against the printed table, that row is where the confusion comes from.

The Fees Around the Building Fee

🏠

Houses Are Exempt From Annual Inspection Fees

Under-known and worth stating plainly: the IRR says single detached dwelling units and duplexes are not subject to annual inspections. If an owner requests one, each listed service costs ₱120. Commercial, industrial and institutional buildings are assessed annually by floor area — ₱120 up to 100 sqm rising to ₱1,200 per 1,000 sqm — and paying more than 30 days late carries a 25% surcharge. We cover the full annual cycle in our commercial compliance calendar.

Why the Fee Is Never What Stops an Application

Owners brace for the fee and are then blindsided by the actual bottleneck. On a 200 sqm house the building fee is roughly ₱1,440 — a rounding error against a multi-million peso build. Applications do not stall on money. They stall on documents.

The permit is assessed against a complete set of plans signed and sealed by the professional licensed for each discipline — architectural by an architect, structural by a civil engineer, electrical by a professional electrical engineer, and so on. The IRR is blunt that the building permit is null and void without the ancillary permits, and each of those needs its own sealed drawings. That is the real cost and the real timeline.

Building anyway is the expensive option. A 100% surcharge of the building fees applies to construction without a permit, with staged surcharges of 10%, 25%, 50% and 100% where work began while the application was pending — and an unpermitted structure is harder to connect to utilities, insure, mortgage or sell.

A Note on These Figures

The building fee brackets, the worked example proving residential fees are flat-rate, the cumulative commercial method and its sample computation, the electrical and mechanical schedules, line and grade, the Certificate of Use or Occupancy steps, Table II.G.1 fixed costing, the annual inspection provisions and the Section 212 surcharges were all read from the New Schedule of Fees and Other Charges in the 2004 Revised IRR of PD 1096. The FSEC rate is Sec. 12.0.0.4 of the 2019 Revised IRR of RA 9514. Not included above: plumbing, electronics and accessory fees, zoning and locational clearance, barangay clearance, and the LGU's own local charges — all real, all variable by locality. The building official makes the final assessment.

Frequently Asked Questions

How much is a building permit in the Philippines?

The government fee itself is smaller than most people expect. Under the 2004 Revised IRR of PD 1096, a single-family house above 150 square metres is assessed at 7.20 pesos per square metre of building fee, so a 200 square metre house carries a building fee of about 1,440 pesos. What makes the total larger is everything around it: the electrical, mechanical, plumbing and electronics ancillary permits, the line and grade fee, the occupancy certificate, and the Fire Safety Evaluation Clearance which is charged at 15 percent of all the fees the building official collects. LGUs also add their own local charges on top, so treat any computation as an estimate until the building official assesses it.

Is the Philippine building permit fee cumulative by area bracket?

It depends on the occupancy group, and this is the single most common error in online permit calculators. For Division A-1 and A-2 residential buildings the fee is NOT cumulative — the whole floor area is charged at the single rate for the bracket it falls in. The IRR's own worked example makes this explicit: a 75 square metre floor area falls in the above-50-to-100 bracket at 4.80 pesos per square metre, and the building fee is simply 75 multiplied by 4.80, or 360 pesos. For commercial and industrial groups the fee IS cumulative: the area is split into sub-areas by bracket, each is multiplied by its own rate, and the products are added.

What is the FSEC and how much does it cost?

The Fire Safety Evaluation Clearance is issued by the Bureau of Fire Protection and is required before the building permit. Under Section 12.0.0.4 of the 2019 Revised IRR of RA 9514, the FSEC for a Certificate of Occupancy is assessed at 15 percent of all fees charged by the Office of the Building Official of the LGU, and it can never be less than 500 pesos. Because it is a percentage of everything else the building official collects, it scales with your project rather than being a flat charge.

What happens if you build without a building permit in the Philippines?

Section 212 of the IRR imposes a surcharge of 100 percent of the building fees for construction, alteration or change of use carried out without a permit. There are also staged surcharges where work began while the permit application was still pending: 10 percent if excavation started, 25 percent at foundation, 50 percent for superstructure up to 2.00 metres, and 100 percent above 2.00 metres. Beyond the money, an unpermitted structure is harder to connect to utilities, insure, mortgage or sell, and the building official can issue a stop-work order.

Do I need to pay an annual inspection fee for my house?

No. The IRR states plainly that single detached dwelling units and duplexes — Divisions A-1 and A-2 — are not subject to annual inspections. If an owner requests an inspection, each of the listed services is charged at 120 pesos. Commercial, industrial and institutional buildings are a different matter: they are assessed an annual inspection fee by floor area, and paying it more than 30 days late carries a 25 percent surcharge.

What are the ancillary permits and are they optional?

They are the electrical, mechanical, sanitary, plumbing, electronics and, where applicable, other discipline permits filed alongside the building permit, each assessed under its own schedule in the IRR. They are not optional and they are not separable: the IRR states that the Building Permit is null and void if not accompanied by the ancillary permits. Each one requires drawings signed and sealed by the professional licensed for that discipline.

The Fee Is Small. The Sealed Plans Are What You Need.

Permit applications stall on documents, not money. AEDO produces the complete permit-ready set — architectural, structural, electrical and plumbing in one package, each sheet sealed by the professional the law requires.

  • Complete design package priced by floor area — fixed figure within 24 hours of telling us your square metres
  • Building permit and all ancillary permits documented together, not chased afterwards
  • Bill of quantities from ₱3,000 so you can tender the build properly
  • Nationwide design and permit documentation; full design-build in Negros Oriental